SCR Power Regulator , THYRISTOR POWER REGULATOR
บริษัทไออีเอส อิเล็คทริค จำกัด ผู้นำเข้าและจัดจำหน่าย โทร.02-1991147-8
SCR UNIT REGULATOR
Installation and ambient conditions:
- When the power regulator is operating, the heat will be generated automatically. Please install the system vertically and leave some empty space on two sides to aviod the temperature inside the regulator rising continuously.
- There must be some ventilation holes on the control box. Please follow the principle of hard air rising to intall the ventilation holes or estra cooling fans.
- Please avoid installing the regulator in the place with high temperature or poor ventilation. Otherwise, the maximum operating capacity must be set lower than 70% of the nominal capacity.
- Avoid installing the regulator in the places with heavy water evaporation, acid, alkaline, or corrosive air.
- Ambient humidity: below 90% RH (no condensation)
- Ambient temperature: -10-45℃
The above numbers are based on the conditions of no erosion, no greasy dirt, and no cover on the heat sink and following the recommended installation guides based on the principle of heat transfer.
Control and applied loading
-
Phase angle control:
continuous phase angle control, steady output, current gauge reading remains steady. But, every half wave will produce harmonic wave.
Applicable loading:
fixed resistance loading, variable resistance loading, inductive loading, IR light bulb. -
Zero crossing control:
distributed zero crossing control, minimum resolution 1 Hz, no harmonic wave, and current gauge reading oscillates.
Applicable loading:
fixed resistance loading.
Wiring and setup notices
www.siaminstrument.com | can cut off power to prevenr personnel from electric shock during maintenance. can cut off supplied loading power when the power regulator malfunctions or the tenperature is higher than pre-set value. Cutting off the power can avoid the system burn down by overheating and prevent more serious damage. can adjust the output power according to the control signal. (This product is embedded with the high-speed fuse, extra fuse is not nccessary.) |
- Standard main circuit setup: main power→molded case circuit breaker→contactors→power regulator→loading.
- The screw must be tightened during the wiring setup to avoid high temperature resulting from bad contact.
- Once the wiring setup is completed the front panel and safety cover must be properly installed before the system is powered up to avoid the electric shock or shot circuit caused by dropped conductive objects.